Resource Assignment

Mike plannerMember for 15 years 8 months
Created
4
2
0

Hi All, 

 

Can i know why i can see the resource on each day? 

 

For example, i have 4000 unit assign to activity A1010 but i only can see 800. I have 5 days on that activity so it should be 800, 800, 800, 800, 800 

 

Thanks

Mike 

 

 

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi, set the resource analysis

    Hi, set the resource analysis to daily in the user preferences.
  2. 0
    Mike planner ·

    Hi,  Thank you for the reply.

    Hi, 

     

    Thank you for the reply. i checked, it was set to Day. It doesnt show the resource on day on resource assignment tho

     

     

    Many thanks

    Mike

  3. 0
    Raymund de Laza ·

    Assign linear resource curve.

    Assign linear resource curve.

  4. 0
    Zoltan Palffy ·

    if it a a LOE it will stack

    if it a a LOE it will stack it on the 1st day unless you assign a curve to it

Log in or join to reply