Resource Assignment on Activity Completed or in Progress
In the Open Standard
Mike plannerMember for 15 years 8 months
- Created
- 2
- 1
0
Hello,
I am applying resources to the activities in progress or completed but the actual is not showing on the activities that have been completed or in progress
Screen 1 - This is before the resource is applied
Screen 2 - After i applied resource to the activity with original duration 15d, the budgeted labour unit shows 15, remaining labour unit shows 4 which are correct but the Actual labour unit is not showing anything. The actual suppose to show 11
Thnaks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?