Skip to content

Cost

Sai Krishna RajuMember for 7 years 3 months
Created
3
2
0
Why ,at completion cost is different from budgeted total cost . The cost is increased at completion cost from budgeted cost

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    go to Projects click on the

    go to Projects click on the calculations tab on the rigth under resource assignments

    make sure that under 

    When updating actual Units or Costs that 

    Subtract Actual from At Completion is checked

  2. 0
    Sai Krishna Raju ·

    i Checked it is Clicked even

    i Checked it is Clicked even then, At completion Cost Is more than Budgeted Cost

  3. 0
    Zoltan Palffy ·

    put in the actual then adjust

    put in the actual then adjust the at completion make it equal the budgted costs 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?