Assigning Cost in P6

Mike plannerMember for 15 years 8 months
Created
1
3
0

 

Hi, 

 

Can i know if i assign the cost correctly in P6? 

I am assignning a fixed price lump sum to my activities.

Firstly, i set the labour budgetted unit to $1/day 

I then, i set the budgeted unit to 43,750.00 so my cost for that activity is £43,750.00. 

With this method, i can use the histograme to see my cost and when i progress the activities, i can see the remaining cost, budgetted cost and actual cost. 

I am not sure if i am doing it right method? can anyone please enlighten me please. 

The problem with this methid is i have 2 resources in the programme. 

 

Many thanks

Mike 

 

 

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    whay do you have 2 resource

    whay do you have 2 resource where 1 can hold both values of manhours and costs 

Log in or join to reply