Assigning Resource

Mike plannerMember for 15 years 8 months
Created
2
3
0

Hi, 

 

I want to assign a new resoure an activity. Can i know why it will changed my budgetted unit? I can see my budgetted Activity Cost is 395050 but when i assign a new resource, it splitted or share my bugeted unit. 

 

How do i prevent this from happend when i assign a new resource?

 

Thanks

Mike 

 

 

 

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    it did nto split your budget

    it did nto split your budget what it does by default is if in your resources your max units/time isset to 8 hours per day it multiplies 8 times the duration to get your budgeted manhours. You can then revise the budgeted manhours as needed. 

  2. 0
    Zhang Haixiang ·

    please check "duration

    please check "duration Type" 

    set to "fixed duration and Units/Time"

    and then if you add a new resource, the budget will be calculated as duration*Unit/Time

    for example, you have an activity with 10 days duration, and you add a resource A (8.00/day) to it, then the budget will be 10*8=80.

    if you add another resource B (4.00/day) to it, then the budget will be 10*4=40, it will not share the budget from resource A

     