Resource Creep

Robert CorranMember for 22 years 10 months
Created
1
4
0

We have some programmes in Primavear v 16.2 which when scheduled shows the resource dates outside the book ends of the activity they are assigned to, e.g. and activity could be 1st Jan to 10th Jan, say you claim 50% schedule the prograham on a week it pushes the resoure allocation past the remaining end date of the activity, anybody help with this please

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Robert,You should check

    Hi Robert,

    You should check the Project Details, Resources: is the "Drive activity/task dates by default" activated or not?

    If not, resources may work longer than the task duration

    Alexandre