Resource Assignment

Chris RymerMember for 16 years 4 months
Created
3
5
0

I am trying to change the budgeted units of a resource in the Resource Assignment spreadsheet but it is greyed out. I have another Project where I can do this but I'm struggling in the new one. Everything appears to be correctly set, such as the Duration type but unfortunately I can't amend anything. 

 

Any advice is appreciated

3 replies

Oldest first
  1. 0
    Chris Rymer ·

    I have now realised that the

    I have now realised that the spreadsheet is greyed out after a specific date. If I move an activity before this date, I can edit the spreadsheet, if I move it later, I can't

  2. 0
    Chris Rymer ·

    I have now realised that the

    I have now realised that the spreadsheet is greyed out after a specific date. If I move an activity before this date, I can edit the spreadsheet, if I move it later, I can't

  3. 0
    Zoltan Palffy ·

    I beleive that you are taking

    I beleive that you are taking about actuals here ?