Skip to content

Transfer Progress between 2 Programmes

Mike plannerMember for 15 years 8 months
Created
4
4
0

Hello All, 

 

I have progresss a programme and added some new activities as Rev 08, progressed as at 14-Feb-20 

However, my previous progress is Rev 07, which was progressed on the 17-Jan-20. 

Can i know if there is a quick method that i can transfer my progress from Rev 08 to Rev 07a? 

 

Many thanks

Mike 

4 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Don't you just make a copy of

    Don't you just make a copy of Rev 08 and then delete the new activities?

  2. 0
    Mike planner ·

    Hmnn... not that easy,

    Hmnn... not that easy, because i have changed some duration and logic. 

    I am wondering if its possible to open 2 programmes and use the global change to transfer the progress from 1 WBS to another 

     

    Many thanks

    Mike 

  3. 0
    Alexandre Faulx-Briole ·

    Hello Mike,I would rather

    Hello Mike,

    I would rather export both schedules to Excel with all the necessary fields, make the adjustments there, then re-import the "new" schedule into P6

    Alexandre

  4. 0
    Zoltan Palffy ·

    open Rev 8 and make rev 7 a

    open Rev 8 and make rev 7 a baseline

    then select maintain baselines and select update

    then from here you can choose what to update all activities or a filter or additional update options under Update options 

    pick and choose what to update 

    when you are done select Restore to put REV7 back into the selectable projects

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?