How do you add your first resource to a blank system? + button is grey under Enterprise Resource

John ReevesMember for 13 years 5 months
Created
2
4
0

How do you add your first resource to a blank system? + button is grey under Enterprise Resource.  I know how to add normally when there is an existing resource dictionary.  It has been a while but I vaguely recall you have to have activity code and roles codes or something weird to add a new item.  I go to Enterprise Resource and all the buttons are greyed out.  It is a new corporate system over Citrix, so maybe it is an admin issue.  I can add resource codes and cost account codes, but the resource.  It does not matter if I filter by "all resources", because there are none.

2 replies

Oldest first
  1. 0
    Rashid Iqbal ·

    John, It will be an admin

    John,

     

    It will be an admin issue; you will need the privilages to add the resources.

  2. 0
    John Reeves ·

    You are correct, people get

    You are correct, people get crazy with those controls - that is a basic funtion.  Thanks for answering.