Transfer Progress between 2 Programmes
- Created
- 3
- 5
Hello,
I have 2 programmes
1) Client Programme - Later completion date
2) Internal Programme - Earlier completion date
99% of ACTIVITY IDs are the same between the 2 programmes.
Is there a way to copy the progress such as from one programme to another?
I always update the Client Programme first and it will take me hours to do the progress updates. Is there a way i can transfer the progress to the Internal Programme. I am not sure how, i think maybe open the 2 programme then using global change but not sure what settings should i use. Or use excel to transfer progress? Again, not sure how do i do that
Many thanks
Mike
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?