Primavera EPPM Test Environment Permissions

Steven ReedMember for 17 years 1 month
Created
2
3
0
I have Primavera EPPM installed on a test server. I have created an EPS, OBS, and user security privileges on the test server. When my IT department moves me to the ‘live’ (or some call it a production) environment. Can I copy the work I created in the test environment to the production environment? I don’t want to perform rework when we move to the live server.

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I do not believe so

    I do not believe so 

  2. 0
    Santosh Bhat ·

    Ask them to copy the entire

    Ask them to copy the entire Database, that's actually much easier work than to copy the contents from within P6. You'll just have to modify the names of the DB you use to connect to.

Log in or join to reply