Skip to content

Problems in importing Excel files

Mohamed GomaaMember for 16 years 10 months
Created
3
3
0

Hi Everybody ,

I exported a resource assignement excel file to change budgeted units and other data, when importing the resource is doubled (as shown in the attched image) , i recalculated the assignement costs , but still i will have to manualy remove the doubled resource and this will be a tediuos process as there is a lot of af activities .

Hope to find a fix to this problem.

Regards

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    go to Projects DIRECTORY and

    go to Projects DIRECTORY and make sure that your project is open

    then click on teh Resources tab at the bottom then look on the lower left where it says Resource Assignment

    UNCHECK Resources can be assigned to the same activity more than once. 

  2. 0
    Mohamed Gomaa ·

    Thanks Zoltan , it

    Thanks Zoltan , it worked.

    Regards

  3. 0
    Zoltan Palffy ·

    of course it worked

    of course it worked

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?