Changing activity start/finish date and duration after being baselined

Troon SigmaMember for 6 years 6 months
Created
3
3
0

Hi,

Suppose plan has been created and baselined. Actual data has also been entered. 

Now, I realize one particular activity had its start/finish date entered very wrong. Is there a way now to change those planned dates?

 

thanks

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,Go to Project, Assign

    Hello,

    Go to Project, Assign baseline; remove the baseline from Project Baseline and User Baselines when necessay

    Go to Project, Update baseline; select the baseline and click Restore to convert the baseline into a new independant project

    Open this project, and edit the activity you are mentionning, then re-schedule the project

    Open the "current"project again, P6 will close the "new" project

    Go to Project, Update baseline; click Add, select the second option and use the "new" project as the baseline for the "current" project

    Take care, Stay home

    Alexandre

  2. 0
    Troon Sigma ·

    Thanks Alexandre !!

    Thanks Alexandre !!

  3. 0
    Raymund de Laza ·

    Hi.Make Sure that Planned

    Hi.

    Make Sure that Planned Dates = Current Dates, Do this in Global Change.

     

    Regards.