Specify the interval to summarize and store resource spreads

Planner PlannerMember for 11 years 2 months
Created
7
4
0

Dear Members

Could you please explain to me how does the "Specify the interval to summarize and store resource spreads" function works?

I read about it but nothing happen when i changed options.

Please help me with explains and template to understand it.

7 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    do you have resources ?are

    do you have resources ?

    are you using resources ?

  2. 0
    Planner Planner ·

    Yes of course

    Yes of course

  3. 0
    Zoltan Palffy ·

    did you then right click on

    did you then right click on the project and select summarize project  ?

  4. 0
    Planner Planner ·

    Of course. Please explain to

    Of course. Please explain to me step by step what should i do to see change

  5. 0
    Zoltan Palffy ·

    do you have financial periods

    do you have financial periods set up ?

  6. 0
    Alexandre Faulx-Briole ·

    Hello Zoltan,Where does P6

    Hello Zoltan,

    Where does P6 display the result of the summarization? I am working with P6 v19.12 Stand-alone with a SQLLite database

    Is it possible to delete the result of the summarization?

    Thank you,

    Alexandre

  7. 0
    Zoltan Palffy ·

    You can see summarized data

    You can see summarized data in the projects directory. After you summarize your project