How do you get around the required (changing)WBS import export requirement/issue?
- Created
- 4
- 2
How do you get around the required (changing)WBS import export requirement/issue? i must be missing something. It is crazy that you cannot import the cost accounts and costs. I am simply importing the costs from an original file to a later file of the same name. Costs import fine. I will only import the cost accounts if you also import the WBS - and being that the WBS uses the project name, even though the same file that rev number is different and over-writes the WBS and blanks out most of it because of the slight name difference - how crazy is this. Let me know if a way around this, I must be missing something. Its crazy, why not just activity ID's like it used to be?
4 replies