Hi All,

I'm in the process of building a fully resource loaded schedule and have recently been advised that I need to apply a 6% internal inventory charge to all materials to recoup internal stores costs.

The obvious answer is to adjust the price / unit for each material but that is not possible as these resources are already in use by multiple teams where this 6% rate doesn't apply. Total cost for all resources is calculated costs x units but I'm hoping someone can advise me as to how I could create and apply this 6% charge across the relevant materials.

Cheers

 

3 replies

Oldest first
  1. 0
    Mohamed Nizam ·

    Is any way to material

    Is any way to material resource as primary resource Second how to assign of unit of measure such as hour for labor and non--labor Third in resource tab of activity details of update primary resource is any setting to automatically update other resource
  2. 0
    Zoltan Palffy ·

    Is any way to material

    Is any way to material resource as primary resource - thats depends on if the # Units of the material is driving the activity

    Second how to assign of unit of measure such as hour for labor and non--labor - yes go to the resource and look under the  

    details tab and there is a drop down there for unit of measure. If you do not see the one you want you can add it by going to Admin then Admin Categories then Units of measure 

    Third in resource tab of activity details of update primary resource is any setting to automatically update other resource

    go to Projects and on the Resources tab under Resource Assignments set the settings there

  3. 0
    Zoltan Palffy ·

    filer for what you want to

    filer for what you want to change

    go to tools

    global change 

    on the right select New

    up top under Slect Subject area change that to Activity Resource Assignments

    where resource id name equals whatever the resource name is

    then budgted costs = budgted costs * .06

     

    On the right select change 

    then on the bottom select commit Chnagest

Log in or join to reply