Filter Conditions For Activity Codes Not Copying With File
In the Open Standard
Chris LothianMember for 19 years 5 months
- Created
- 4
- 2
0
Hi All,
Do you know why it is that when I copy a project within the database and paste it within the database, the filters in the new file have lost the conditions that relate to activity codes?
- They are user defined filters.
- The activity codes are project level.
- The activity code copies across OK (and remains allocated to the activities).
- The filter copies across (it just loses its conditions relating to activity codes).
- Where the filter has multiple conditions, the conditions not related to activity codes copy across, but the it still loses its conditions relating to activity codes.
- I’ve tried saving the filter as a layout filter.
- I’ve tried saving the layout (with the layout filter), exporting from original file, then importing to new.
- The contract is for a large company that's operating a enterprise db (where there's a massicve list of global filters) and I can only set things at project level.
Any ideas please?
Thanks in advance,
Chris
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?