Project List in Primavera

Athar HashmiMember for 17 years 6 months
Created
6
4
0

Hi,

I am trying to import activities and resources from excel (.xlsx) to primavera. After selection of excel file when a popup appear to select the project, where should I want to import the data, that project list window appear blank, without any list of P6 project. Kindly let me know the reason and troubleshooting for this.

Thanks.

Athar Hashmi

6 replies

Oldest first
  1. 0
    Santosh Bhat ·

    It has to do with the

    It has to do with the database security privileges for you. To import XLSS files you need both the Global privilege to import (which you must have as you get this far), and also be a Project Super User as the project security profile assigned to the responsible manager of that project. 

     

    You'll need to contact whimever administers the users in the P6 database you're working in to sort it out.

  2. 0
    Athar Hashmi ·

    I am not a superuser though i

    I am not a superuser though i have the global privilege and responsible manager assigne to me. So that would be the reason <AdminSuperuser>.

    Thank you very much Santosh

  3. 0
    Zoltan Palffy ·

    Under the security profile

    Under the security profile under global profiles you need to make sure that the import XLS box is checked

  4. 0
    Athar Hashmi ·

    Hi Zoltan, under the secuirty

    Hi Zoltan, under the secuirty profile -> Global profile -> Import .xls is checked, while in main import screen it gives the option to select spreadsheet with ".xlsx" extension. So there is conflict between the file extensions.

    I have saved the file with .xls then imported it. In this case p6 is not recognising the file and all the option to import activities or resources, etc were disabled.

    Conflict of file extension might be a reason?

  5. 0
    Santosh Bhat ·

    As I noted earlier, just the

    As I noted earlier, just the Global privilege is not enough. You also need to be assiged as Project SuperUser in the project profile of the REsponsible Manager for that project.

  6. 0
    Zoltan Palffy ·

    Santosh is correct

    Santosh is correct 