Monthly Duration Not Giving Fixed Monthly Hours
In the Open Standard
Troon SigmaMember for 6 years 6 months
- Created
- 5
- 1
0
Hi guys,
I have the following settings:
1. In Calendar, monthly hours are 150
2. Duration Format (in User Preferences) is set to Months.
Now, when i enter activity duration to 1 month, I see 150 monthly hours, which is fine. But when i put 2 months duration, i get 166 hours in first month and 134 and second month. (although the total is 300, which is fine)
Similarly, if i put 3 month or 4 month duration, i am not getting fixed 150 hours for each month.
Fixed hours should not be expected for each month? And how can i fix the monthly hours?
Thanks
5 replies
Oldest firstLog in or join to reply