Color Activity not meeting Baseline

Jithin KambhikanamMember for 15 years 6 months
Created
1
3
0

Hello Everyone,

 

Is there a way by which the Activity Bar which didnt meet the Basline Date can be highlighted in a different colour Say like Orange.

 

Red coloured bar is critical activity, but I would like to show activities which hasnt met the baseline date in Yellow.

 

Any chance ?

 

Thanks

Jithin

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Jithin,you can create a

    Hi Jithin,

    you can create a new bar in wich you will assign a filter based on the "Variance BL1 Start Date", or "Variance BL1 Finish Date", or both

    Alexandre