Variance Showing in p6 even though Activity no Budget

Patrick WalshMember for 13 years 1 month
Created
1
3
0

hello

I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.

Please help, it has to be a setting issue i think....

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    if it has a variance it must

    if it has a variance it must be comparing against something do you have a baseline attached ?

    see if there is an actual cost  or a cost to complete ?

    if there are values here it will still show a variance

    look at previous period costs 