Importing a Resource Assignment Excel File to P6 Schedule
In the Open Standard
Khalid AlshurafaMember for 5 years 10 months
- Created
- 3
- 5
0
Gents,
After making an excel file export from the schedule, I have tried to import again to the same schedule.
However, when I reached the step at which I should select the project to import for, the screen was empty and didn't give any project to select. Hence, I have tried to do the import from a different user account and to the same project and didnt face this issue, and the issue appeared only at my user account.
Does any one has a solutioin for this
Thanks,
3 replies