Format the Relationships Lines in Primavera P6 Version 8.2
- Created
- 5
- 3
By default in Primavera P6 8.2 -
The color of the relationship represents:
Ø Red – Critical and therefore a Driving relationship,
Ø Solid Black – Non-Critical Driving relationship and therefore has Free Float,
Ø Dotted Black – Non-Critical Non-Driving relationship and has Free Float, and
Ø Blue – a selected relationship and may be deleted.
But in my computer its showing both driving and non-driving relationship as non-dotted red lines - How to format the relationship display to make Primavera show non-driving relationships as black dotted lines?
And also In General how to Format the Relationships Lines in Primavera P6 Version 8.2?