Resource Movement Arrows Grayed Out
- Created
- 14
- 2
14 replies
Oldest first- 0VKVikas Kulkarni ·
Dear Sir,Thanks for your
Dear Sir,
Thanks for your reply.
I am using Primavera Standalone P6 Professional Release - 16.1 with PMDBSQLITE Database
The Admin Menu has only the following options -
1. Admin Preferences
2. Admin Categories
3. Currencies
4. Financial Periods
The other options i.e. -
1. Users
2. Security Profiles
3. Timesheet Dates
ARE MISSING
With Best Regards.
- 0VKVikas Kulkarni ·
Dear Mr. Santosh Bhat,The
Dear Mr. Santosh Bhat,
The filter is "ALREADY SET TO DISPLAY ALL RESOURCES".
I watched 2 YouTube Videos where the Presentor is also having these arrows grayed out in the video - So I think the Standalone Version seems to have these arrows grayed out - Maybe - I am not sure.
Thanks & Regards.
- 0AFAlexandre Faulx-Briole ·
Vikas,Look at the Resource ID
Vikas,
Look at the Resource ID colum header in the Resource Workspace:
you will see a small symbol on the right side of the header: click on the symbol until you see 3 small lines instead of a triangle; then you will be able to move the resources by using the 4 blue arrow buttons of the tool bar on the right side of the screen
this has nothing to do with User rights, and a stand-alone P6 running with SQLlite database has no access to user rights and profile
Alexandre
- 0AFAlexandre Faulx-Briole ·
Vikas,Look at the Resource ID
Vikas,
Look at the Resource ID colum header in the Resource Workspace:
you will see a small symbol on the right side of the header: click on the symbol until you see 3 small lines instead of a triangle; then you will be able to move the resources by using the 4 blue arrow buttons of the tool bar on the right side of the screen
this has nothing to do with User rights, and a stand-alone P6 running with SQLlite database has no access to user rights and profile
Alexandre
- 0VKVikas Kulkarni ·
Dear Alexandre Faulx-B,
Dear Alexandre Faulx-B,
I have pasted 2 Screen Shots of my my Resource ID Column Header.
If I click on the small triangle as shown in the upper image it gives the options as shown in the image &
if I click the small triangle as shown in the below image then P6 just Sorts the Resource ID's columns.
But there is no option where the small triangle changes to 3 lines.
Thanks & Regards.
- 0VKVikas Kulkarni ·
Dear Alexandre Faulx-B,
Dear Alexandre Faulx-B,
I have pasted 2 Screen Shots of my my Resource ID Column Header.
If I click on the small triangle as shown in the upper image it gives the options as shown in the image &
if I click the small triangle as shown in the below image then P6 just Sorts the Resource ID's columns.
But there is no option where the small triangle changes to 3 lines.
Thanks & Regards.
- 0SBSantosh Bhat ·
Vikas, The Column header for
Vikas,
The Column header for Resource ID is a Tri-State toggle. It can be clicked three times, once for sorting Ascending Alphanumerically, Again for Descending Alphanumerically, and thirdly for Hierarchically based on the Resource Structure.
Make sure you click this three times to go through each option and you should see the indent arrows appear when it is displaying the hierarchical structure.
- 0VKVikas Kulkarni ·
Dear Mr. Alexandre Faulx-B &
Dear Mr. Alexandre Faulx-B & Mr. Santosh Bhat,
It worked - "The Resource Movement Blue Arrows" have appeared - Image Attached.
I had actually accidentially turned on the Resource Group & Sort by Primary Role. Therefore the Tri-State Toggle was alternating only between the first 2 states and not showing the third state i.e. 3 Lines - Indent arrows - Hierarchical Structure.
I did not know that this Column Header is "A Tri-State Toggle".
Thanks A Lot To Both Of You,
With The Very Best Regards.
- 0VKVikas Kulkarni ·
Thanks A Lot To Dear
Thanks A Lot To Dear Mr. Zoltan Palffy too.
With The Very Best Regards.