Update Problem on Duration Types
In the Open Standard
Boran UcarMember for 6 years 10 months
- Created
- 3
- 3
0
I've created an activity and set it's duration type as fixed duration and units/time and percent complete type to physical. I've assigned two resources as 20/d units/time, 1000 units and 50 durations.
Later on, I've updated schedule on 25th day of this activity and entered actual units as 800.
Remaining duration still seems 50 days and At complete duration is 75 days. Isn't it supposed to remain 50 days as it's duration type is fixed duration?
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?