Skip to content

Creating Resource Curves for Labour Loading Profiles

Rodney JonesMember for 14 years 4 months
Created
0
3
0

 

Hello All,

I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.

Enterprise > Resource Curves > Add or Modify.

I have a 3 month duration activity with a budget spend profile of 25%, 50%, 25% but when I set the Resource Curve profile as shown, it ends up front loading all the labour in the first month.

How do I make this work?

Thanks,

 

Rod

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?