Creating Resource Curves for Labour Loading Profiles
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 3
- 2
0
Hello All,
I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.
Enterprise > Resource Curves > Add or Modify.
I have a 3 month duration activity with a budget spend profile of 25%, 50%, 25% but when I set the Resource Curve profile as shown, it ends up front loading all the labour in the first month.
How do I make this work?
Thanks,
Rod
3 replies
Oldest firstLog in or join to reply