Creating Resource Curves for Labour Loading Profiles

Rodney JonesMember for 14 years 4 months
Created
3
2
0

 

Hello All,

I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.

Enterprise > Resource Curves > Add or Modify.

I have a 3 month duration activity with a budget spend profile of 25%, 50%, 25% but when I set the Resource Curve profile as shown, it ends up front loading all the labour in the first month.

How do I make this work?

Thanks,

 

Rod

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Sorry I just have to ask did

    Sorry I just have to ask did you assign this resource CUVREe to that activity ?

  2. 0
    Rodney Jones ·

    Hi Zoltan, YEs, Applied at

    Hi Zoltan, YEs, Applied at the Activity level when the Resource was assigned and then Recalced the project.

  3. 0
    Zoltan Palffy ·

    do you have more than 1

    do you have more than 1 resource assigned to this activity ?

    is the resource on the correct calendar ?

    what is the duration tyoe ?

Log in or join to reply