Earned value columns based on physical progress
In the Open Standard
Troon SigmaMember for 6 years 6 months
- Created
- 2
- 3
0
Hi,
My activities' % Complete Type is set to "Physical". I enter physical progress of the activities, however the earned values do not change. If i enter duration progress e.g remaining duraiton or labor hours, the earned value change.
My question is, the earned value columns are not linked with physical progress, even if Complete Type is physical?
Thanks
2 replies