Earned value columns based on physical progress

Troon SigmaMember for 6 years 6 months
Created
2
3
0
Hi,
 
My activities' % Complete Type is set to "Physical".  I enter physical progress of the activities, however the earned values do not change. If i enter duration progress e.g remaining duraiton or labor hours, the earned value change. 
 
My question is, the earned value columns are not linked with physical progress, even if Complete Type is physical? 
 
Thanks

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    no they ar enot linked what

    no they ar enot linked what you can do is creat a global chnage where the duration % complete is equal to the physical % complete.

    Here is how

    got to tools

    global change

    on the right select new

    Where Physcial % is not equal to 0

    Then 

    Duration % Complete  =    Physical % Complete

     

    on the right select Change

    then on the bottom right select Commit Changes

     

     

  2. 0
    Rafael Davila ·

    EV & Performance % Complete