Physical % complete for milestone date
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 1
- 2
0
Hi Planners
I am updating a schedule and the first activity is start milestone, when I enter the actual start date, the percentage complete does not change to 100% and I tried to fill it manually but it does not work. It works for other activities.
Regards,
Muataz
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?