Physical % complete for milestone date

Moutaz AldeibMember for 22 years 9 months
Created
1
2
0

Hi Planners

I am updating a schedule and the first activity is start milestone, when I enter the actual start date, the percentage complete does not change to 100% and I tried to fill it manually but it does not work. It works for other activities.

 

Regards,

Muataz

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    in the general tab is the %

    in the general tab is the % complete type set to physical

    did you check the Started box next to the date ?

Log in or join to reply