P6 Professional R19.12 Importing a WBS from Excel
- Created
- 2
- 3
Hello,
I would like to import a WBS from MS Excel to P6 Professional. I attempted to do this by first exporting a P6 schedule to MS Excel so make sure I have the correct format. Unfortunately, P6 Professional does not import Excel data that has a column heading including an (*). This means P6 will not import WBS Path, WBS Name, and WBS Category. Also, for some reason I was unsuccessful importing the WBS Code as well.
What is the most efficient way to import a WBS from MS Excel to P6 Professional? My WBS is over 400 lines. I would also be nice to include the Summary Scope of Work with the WBS.
Am I better off manually inputing the WBS directly into P6 Professional?
Any input?
--Steve
2 replies
Oldest firstLog in or join to reply