P6 Professional R19.12 Import Resource Assignment from Excel
- Created
- 3
- 4
My ASST SCN has a payrate of $39.62 as diplayed below.
I export the below schedule with the respective activity resource assignments.
The exported TASKRSRC worksheet displays as below.
I import this Excel to a schedule with no resource assignments.
When the Resources and Resource Assignments are imported I get the below.
Why does the Price/Unit import as $1.00/h^?
And I cannot manually change the Price/Unit of Assistant Scientist/A.
The only way to correct the Price/Unit is to delete the resource assignment and re-assign the resource. But this defeats the purpose of importing the Resource Assignmnent from Excel.
Any thoughts?
--Steve
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
