How do tie together the P6 Schedule, Submittal Schedule Log, & the SOV? they have redundant info - a code?
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 1
- 2
0
How do tie together the P6 Schedule, Submittal Schedule Log, & the SOV? they have redundant info - a code? A code could tie them together but how? Sometimes multiple schedule items belong to only one SOV and vice versa - you could put the sched id in the sov and the sov number in the schedule but couldn't there be one similar code? I think InEight might do something like this but I am not sure.