Primavera Visualizer Scheduler Compare - can you export it to excel?

John ReevesMember for 13 years 5 months
Created
1
3
0

Primavera Visualizer Scheduler Compare - can you export it to excel?  It has gotten better, it is still weird and clunky though - I can only seem to print of the screen.  Can you export to excel, I tried to copy and paste to excel - that did not work too well.

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·

    Yes you can. Go to Option and

    Yes you can. Go to Option and select General Tab. Select CSV and select the file destination and file name. Click Save and Draw. Then go to the folder where you save. Double click the csv file and it will open in Excel. See below: P6-Schedule-Comparison