activity duration 4.4d instead of 5d
- Created
- 4
- 3
Hi,
When I add a new activity, duration is not 5 but 4.4days.
This issue is obviously coming from the calendar because it has been modify to 8h/day instead of 7h.
This is not a global but a project Calendar.
I checked my Project settings calendar for new activities by default and it is the one needed : 8h/day.
I checked the calendar parameters and it is correctly filled with 8hours in the workweek or in the timeperiods tables.
I don't know what I am doing wrong and where is the solution.
If anybody had the solution, I would be very gratefull to you.
For information, we are working on P6V19.