Resource Leveling

Hamid TavassoliMember for 13 years 1 month
Created
8
4
0
Hello everyone,
 
I am facing a problem in resource leveling. After completion the scheduling, I faced with overallocation. As a result, i defined priority and used leveling, but unfortunately no change is happened. anybody has idea what could be the reason?
 
Thanks

8 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Hamid,When you run Level

    Hi Hamid,

    When you run Level Resource (shift+F9). Did you select:

    1. Automatically Level Resources when scheduling
    2. Preserve schedule early and late dates
    3. Level all resources

    Also did you select the field names you use for levelling priorities?

  2. 0
    Hamid Tavassoli ·

    Hi Rodel,I selected “Preserve

    Hi Rodel,

    I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.

  3. 0
    Hamid Tavassoli ·

    Hi Rodel,I selected “Preserve

    Hi Rodel,

    I selected “Preserve scheduled early and late dates” and some change has happened, but still, I am faced with over-allocated resources in some parts.

  4. 0
    Rodel Marasigan ·

    Hi Hamid,As you mentioned,

    Hi Hamid,

    As you mentioned, your setting is Fixed Units. Is the activity itself is over allocated? It so then overallocated resource on activities will not move or will not level.

  5. 0
    Hamid Tavassoli ·

    Hi Rodel, If an activity

    Hi Rodel,
     
    If an activity itself is over-allocated, the duration will not change after leveling to resolve the overallocation?
    I defined a small project for better monitoring. Even in overlapping activities, when I run level resources (Considering the 3 items you mentioned earlier), no change occurs. is there any special adjustment needed before leveling that may I have forgotten?
  6. 0
    Rodel Marasigan ·

    Hamid,Make sure that no

    Hamid,

    Make sure that no overallocated on each activities as it will not move because it is already overallocated. Overlaping activities is fine as long as it will be level accordingly. Make sure the maximum limit is set ex: say 5 res x 8hrs/day = 40hrs/day

  7. 0
    Hamid Tavassoli ·

    Rodel,Thank you very much for

    Rodel,

    Thank you very much for your help.I will be so happy if I can be in direct contact with you, if possible.
    Email: Hamid.tavassoli@gmail.com
  8. 0
    Hamid Tavassoli ·

    Rodel,Thank you very much for

    Rodel,

    Thank you very much for your help.I will be so happy if I can be in direct contact with you, if possible.
    Email: Hamid.tavassoli@gmail.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?