Dates we need to ignore
- Created
- 1
- 3
I set up the usual start, finish (better than ES,EF) and then the Later Start, Late Finish. For simple things like my Start Milestones that have ACTUALS, I get a value in the Late Start and even worse gives me a big float bar. There should be no float on an ACTUALIZED Activity. So this is just data we have to ignore? Where does this date come from / what does it mean? I assume some people set up UDF fields and just copy the remaining work to be less complicated for novices but this seams so strange it makes me feel I am not setting up correctly. I used P3 for so long, sometimes the differences still confuse me.