How to upload a set of Activity Codes?
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 0
- 3
0
Hi All,
I have created some Activity Codes to be assigned for accounting purposes. The first stage was easy as there were only 8 groups and maybe 5 or 6 codes within each group.
Sample: Code Value Description
2 Tailings/BPF Area
2.1 C-12394-01-02-05-07
2.2 C-12394-01-02-05-06
2.3 C-12394-01-02-04-04
2.4 C-12394-01-02-05-07
2.5 C-12394-01-02-05-07
2.6 C-12394-01-02-06-03
2.7 C-12394-01-02-04-06
but now the request is to expand the listing and groupings to an additional level as below:
| 2 | 2 | Tailings/BPF Area | ||||
| 2.1 | C-12394-01-02-05-06 | 2.1 | Bulk Earthworks BPF area | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.1 | Bulk excavation of BPF pad & roads areas to subgrade - spoil to material to Water treatment plant area (Subject to remeasure against actual) | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.2 | Excavate and trim Drain A | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.3 | Excavate and trim Drain B | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.4 | Supply, Place, Compact and trim pavement to BPF Pad & roads | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.5 | Supply & Installation of culverts & head walls to Drain A & B | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.6 | Supply, place geofabrics & rock works to Drain A & Drain B outlets | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.7 | Supply and installation drain A Gabion wall | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.8 | Form road side safety bunds | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.9 | Excavate, form and pour concrete spoon drain | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.10 | Drainage bund at CV1097 | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.11 | Supply and Installation of conduit services (Subject to remeasure against actual) | |||
How can I upload the codes spreadsheet?
Thanks,
Rod
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?