How to upload a set of Activity Codes?
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 7
- 3
0
Hi All,
I have created some Activity Codes to be assigned for accounting purposes. The first stage was easy as there were only 8 groups and maybe 5 or 6 codes within each group.
Sample: Code Value Description
2 Tailings/BPF Area
2.1 C-12394-01-02-05-07
2.2 C-12394-01-02-05-06
2.3 C-12394-01-02-04-04
2.4 C-12394-01-02-05-07
2.5 C-12394-01-02-05-07
2.6 C-12394-01-02-06-03
2.7 C-12394-01-02-04-06
but now the request is to expand the listing and groupings to an additional level as below:
| 2 | 2 | Tailings/BPF Area | ||||
| 2.1 | C-12394-01-02-05-06 | 2.1 | Bulk Earthworks BPF area | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.1 | Bulk excavation of BPF pad & roads areas to subgrade - spoil to material to Water treatment plant area (Subject to remeasure against actual) | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.2 | Excavate and trim Drain A | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.3 | Excavate and trim Drain B | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.4 | Supply, Place, Compact and trim pavement to BPF Pad & roads | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.5 | Supply & Installation of culverts & head walls to Drain A & B | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.6 | Supply, place geofabrics & rock works to Drain A & Drain B outlets | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.7 | Supply and installation drain A Gabion wall | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.8 | Form road side safety bunds | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.9 | Excavate, form and pour concrete spoon drain | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.10 | Drainage bund at CV1097 | |||
| 2.1 | C-12394-01-02-05-06 | 2.1.11 | Supply and Installation of conduit services (Subject to remeasure against actual) | |||
How can I upload the codes spreadsheet?
Thanks,
Rod
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?