Primavera - compareing a positive schedule to a negative.
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 1
- 2
0
Best way to handle the following: Target (same month) has negative float. Revision of same month has no negative float (recovery schedule) - I don't think I can show Target Float, also the Targ. Start and Finish are goofy - I assume that is because they are negative? - Seems odd can only pull 1 set of dates. In P6 16.1 is this a problem they later solved? Have later versions Added more columns? I think the best way to resolve this is to compare from the Neg. Float version to the non-neg. version.
1 reply
Oldest firstLog in or join to reply