Chronological Order

Anu hansMember for 8 years 11 months
Created
1
2
0

I have just started to learn P6. Recently I wrote a small programme in P6 and linked it. Suddenly programme chronological order changed from back to front (last activity on top then earliest activity to bottom) Has anyone got any idea why  this happened please. Any help well appreciated

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    1. if you click on the top of

    1. if you click on the top of any column this will order the data in assending or desending order.

    2. you can also turn off automatically re-organize by going to Tools dissable-automatic re-organization or by pressing the shift ket + the finction key F12

    shift+F12

    3. also if you go to View

    group and sort by and select the sort button on the right you can sort on multiple fields if you wish

Log in or join to reply