Percentage Complete in Schedule - Overall
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 2
- 2
0
Hi All,
Can we show the % complete in tthe schedule by WBS and so get the overall % complete of the Project.
We would be updating the activity % complete but can the WBS show the oerall % complete based on the activity pogress %.
A schedule which has Engineering - Measured in Manhours, Procurement - Measured in Cost, Construction - Measured in Manhours.
I do make the OVerall % Complete and indivigual WBS % complete in Excel.
Waiting for your input.
Thanks
Jithin
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?