Critical Path activities extension.
- Created
- 4
- 2
There is a convention in our company that we don't extend the duration of an activity which is on critical path, to capture the activities which have caused the delay in the program in a better way.
We have a WBS and under that WBS (which is named Change Management) we add those extension of that.
So, basically, if activity A with a duration of 20 days is placed on CPM and is going to be finished in 25 days,we are going to create another activity named A+ with a duration of 5 days.
My questions is if activity A has " activity b", " activity C", and " Activity D" as its successors;
what would be the " successors of activity A, after adding activity A+"
And what would be the predecessor and succsors of activity A+.
Is it going to be like this?
A: Succeesros ==> Activity B, C, D, A+
A+ " Predecessor==> A
A+ : Successor ==> B, C, D?
" Is it important if any of activity B, C, or D are driving predecessors for activity A?
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?