Resource Driven Critical Path Visibility
In the Open Standard
Alex LyaschenkoMember for 15 years 2 months
- Created
- 5
- 6
0
Does anyone already have experience with this Primavera feature annonced in 21.12 release?
Resource Driven Critical Path Visibility.
To aid in the resolution of delayed critical paths before they become project over-runs, P6 Professional can show:
- Activities on up to 30 activity-driven critical paths, calculated on the forward pass, backward pass, or forward and backward passes (with or without resource leveling).
- The activities on up to 30 resource driven critical paths, calculated on the backward pass with resource leveling.
How it actaully work?
Does anyone has an example?
Have Oracle fixed the 'incorrect Total Float' bug when schedule is levelled?
5 replies
Oldest firstLog in or join to reply