Primavera Layouts
- Created
- 6
- 3
Hi All,
I am new to scheduling and I have a question.
Before asking my question, just wanted to give you a notice what we generally do( maybe this is a common proceduer in every office):
There is a baseline of the project which is assigned in " Project Baseline" and there is another one which is for the last month and it is assigned in " primary baseline".
I have updated the schedule in late October and have put all the actuals and everything related to the programme in the software. After that I have baslined the programme and named in for " October" and assigned this baseline for " Primary Baseline".
Now I want to create a layout for myself to see the differences between " September" and " October"
1- Are the assigned baseline Okay? " Project baseline: The main baseline of the project, " Primary Baseline : October's baseline with a data date of 1st of November"
2- What columns should I put there to see the changes?
I know you may say that all of them can be there, but I want the ones which are useful for tracking the changes between these two months.( September and October).
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?