Hello all,
I have a project and I want to check it( I am new to scheduling)
Budgeted total cost : 666,827
BL project total cost : 873,327
Budeted At completion : 873,327
Estimate at completion cost : 1,344,157
Actual cost : 1,177,689
EV: 810,122
PV: 873,327
Remaining total cost : 166,468
Why is there a difference between " Budgeted total cost" and BL Project total cost? And should I match them? How?
What should I do if I want to match " estimate at completion cost" and " Budgeted At completion"