Skip to content

Differences in cost

Abbas RajabpourMember for 4 years
Created
2
3
0

Hello all,

 

I have a project and I want to check it( I am new to scheduling)

 

Budgeted total cost : 666,827

BL project total cost : 873,327

Budeted At completion : 873,327

Estimate at completion cost : 1,344,157

Actual cost : 1,177,689

EV: 810,122

PV: 873,327

Remaining total cost : 166,468

 

Why is there a difference between " Budgeted total cost" and BL Project total cost? And should I match them? How?

What should I do if I want to match " estimate at completion cost" and " Budgeted At completion"

2 replies

Oldest first
  1. 0
    David Kelly ·

    This is Earned Value basics,

    This is Earned Value basics, Abbas.

    Budgeted Total Cost represents the scope of work in the current plan

    BL Project total cost is the same calculation as above BUT from the Project Baseline – it would seem there is about 210,000 less scope in the current plan

    Budget At Completion is from the baseline

    Estimate at Completion can have variable algebra. It seems that in this case it is the Budget at Completion, NOT  factored by the CPI, plus the remaining cost.  This is very optimistic

    Actual cost self-explanatory

    Both Earned value and Planned value are based on the baseline. Since the baseline seems to have 210,000 more cost than the current plan, this discrepancy needs looked at first.  

    Remaining total cost is from the current plan.

    ‘Why is there a difference between " Budgeted total cost" and BL Project total cost? And should I match them? How? – Because 210,000 worth of scope has been removed. Why would you want to hide that?

    ‘What should I do if I want to match " estimate at completion cost" and " Budgeted At completion"’ not sure why you would want to tell lies about productivity, but you could simply overwrite the actual cost with an invented figure……


     

  2. 0
    Abbas Rajabpour ·

    Thanks David for your kind

    Thanks David for your kind words and giving me the details, I have not intention to tell a lie, but this is the proceduer that we take in the office.

    We just update the cost based on what the Construction Leads give us.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?