Resource question = Unit 1/d, budgeted 8 units AC=8, working all 5 days, my p6 histogram chart says 4 for the week? how?
- Created
- 2
- 3
Resource question = Unit 1/d, budgeted 8 units AC=8, working all 5 days, my p6 histogram chart says 4 for the week? how? - shouldn't it 40? Shouldn't the at completion units be 8 units x 9 days = 72? Ok, so if this was saying 8 hrs day x 5 days = 40. But being that it totaling to 8, it is doing less than 1 unit per day so for a week it would 4. So if this was going to take 4 workers per day for 9 days, I would either have to increase Unit/time to 4/d or consider 1 "a crew day". Then that would make sense. But the contractor put 1/d for each labor item. Would they normally have to define what 1/d is? Or if that is crew days how many are in crew?
2 replies