"Update Existing" resources etc - what exactly is being updated? How come all my projects bleed together for resources?

John ReevesMember for 13 years 5 months
Created
1
3
0

 Existing" resources etc - what exactly is being updated?  How come all my projects bleed together for resources?  - If I say "use existing" for calendar or resources - and it changed in update - won't my project not match the original import?

1 reply

Oldest first
  1. 0
    David Kelly ·

    Hmm.  'Bleed together for

    Hmm.  'Bleed together for resources' - this sounds a bit like a query about all projects sharing the same pool of resources. Which is correct, and almost the whole point of an enterprise-wide project management system. You can partition the resource dictionary such that you can emulate project-specific resources.


    If, on import, you chose 'use existing' then the project might not match the original exported project, calendar details, resource availability etc.

Log in or join to reply