How to edit gray boxes in Resource Usage Spreadsheet
In the Open Standard
Huss PSMember for 4 years 2 months
- Created
- 3
- 2
0
Hi All,
I am trying to distribute hours using resource usage spreadsheet. some of the boxes have turned gray and i can not edit them.
Activities haven't started
actual hours are 0
budgeted hours = remaining hours
Refer to activity "Insert seismic bracing" in below snapshot.
Duartion type is Fixed Units. All activities are fixed units and i was able to edit them. Its just these couple of activities.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?