How to edit gray boxes in Resource Usage Spreadsheet

Huss PSMember for 4 years 2 months
Created
3
2
0

Hi All,

I am trying to distribute hours using resource usage spreadsheet. some of the boxes have turned gray and i can not edit them.

Activities haven't started

actual hours are 0

budgeted hours = remaining hours

Refer to activity "Insert seismic bracing" in below snapshot.

 

Duartion type is Fixed Units. All activities are fixed units and i was able to edit them. Its just these couple of activities.

3 replies

Oldest first
  1. 0
    David Kelly ·

    Check out page five of the

    Check out page five of the PDF document 'Using a holiday plan rather than calendar exceptions' that you will find on:

     

    www.p6david.uk/tipnew

     

    Currently the above page not behaving perfectly on Firefox, but fine on Edge

  2. 0
    Huss PS ·

    It Worked!!Great. Thanks for

    It Worked!!

    Great. Thanks for your help.

    The issue was duration type. I changed it from "Fixed Units"to "Fixed Duration & Units"

  3. 0
    Huss PS ·

    It Worked!!Great. Thanks for

    It Worked!!

    Great. Thanks for your help.

    The issue was duration type. I changed it from "Fixed Units"to "Fixed Duration & Units"

Log in or join to reply