ETC different than Budgeted labour units for not started activity
- Created
- 3
- 3
Hello,
So a collegue showed me a weirdd situation in P6: an activity that hasn't started yet, however the estimate to complete labour units are different (lower) than the budgeted labour units. It seems odd for this to happen and I can't think of any explanation, especially for an activity with no actuals. Even the WBS EV caluclation considers ETC = BAT - EV.
Any ideas how is this caused and how to fix it?
Thanks,
_______
Update: Seems like this only happens when assigning an old baseline to Project Baseline, when assgning current project to PB the ETC is correct. What is the explanation?
3 replies
Oldest firstLog in or join to reply