Overall % Complete

Jithin KambhikanamMember for 15 years 6 months
Created
2
1
0

Hi All,

Would like to know if we can show overlla % compelete in PRimavera updated schedule.

I have been progress measuring using excel in which some activities progress is measured by

  • Manhours
  • Cost

But the OVerall weightage is claulated based on the assigned weighate as per Contract for example

Engineering - 15%

Procurement - 40%

Construction - 35%

Commissioning - 10%

 

So can we show this in PRimavera 6 updated schedule ?

Regards

Jithin

2 replies

Oldest first
  1. 0
    David Kelly ·

    You could use the WBS

    You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote.

  2. 0
    Rodel Marasigan ·

    You can create a resources

    You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS